The Whare, Monte Cecilia - Hillsborough
Projects
deconstruction (commercial)

The Whare, Monte Cecilia - Hillsborough

Live

2026

Deconstruction Progress10%
72A Hillsborough Road
Client: Auckland Council
Oct 2026

The Whare - Heritage building Deconstruction

TROW Group has been engaged to undertake the controlled deconstruction of The Whare, a heritage-listed timber building located within Monte Cecilia Park in Royal Oak. The project involves licensed asbestos removal, staged deconstruction, progressive heritage recording and the careful recovery of suitable historic timber and other materials for reuse through the Auckland Council Waste Solutions community recycling project. Works will be carried out in a controlled sequence, with particular attention given to protecting the building's remaining heritage fabric, surrounding park environment, notable trees and public areas.

Project History

The Whare has a history dating back to the early 1900s. In 1902, The Pah became the new home of St John's Collegiate School, and the building was relocated from St John's College in Tāmaki and re-erected at the site. It originally housed a library, a master's room, three dormitories and a bathroom. Additions were made to the western side in the early 1900s, followed by further alterations during the 1950s, including changes to the cladding and windows and the infilling of the front verandah. Following investigations in 2015, 2019 and 2025, the Puketāpapa Local Board resolved on 28 August 2025 to proceed with deconstruction due to the building's deteriorating condition, ongoing vandalism, unauthorised access and the lack of financial viability for restoration for community use. Heritage New Zealand Pouhere Taonga has been consulted, with deconstruction to be staged to allow the building's remaining heritage fabric to be progressively recorded.

As the track has been used over time, some sections require improvement to provide a safer and more stable walking surface. The project has been developed to address these areas while working carefully within the existing environment. The upgrade will retain as much of the existing track and natural environment as practicable, with works focused on improving the areas that require attention rather than unnecessarily disturbing the surrounding landscape.

The Whare. Photograph from Scrap book held as part of the Smallfield Collection at the Anglican Diocesan Archives, Auckland. Evidence of the early 1900s window visible above 1950s window, and the earlier west porch.


The project involves several key stages:

Site Establishment Removing identified asbestos-containing materials under licensed controls. Investigating inaccessible areas where asbestos-containing materials are presumed to be present. Removing general rubbish and non-hazardous debris Progressively recording significant building elements in coordination with the Council-appointed heritage architect. Carefully dismantling the roof, wall framing, internal linings, timber floors and remaining structural elements. Salvaging suitable historic timber and other materials for reuse. Removing remaining piles, clearing debris and reinstating affected grassed areas.


Our Approach

The Whare project requires a carefully coordinated approach to heritage deconstruction, asbestos management and environmental protection. TROW Group will work alongside specialist asbestos removalists and the Council-appointed heritage architect to ensure the building is dismantled in a controlled sequence, with significant construction details recorded as they are exposed. Particular care will be taken to manage dust, debris, noise, plant movements and public access while protecting the surrounding park and minimising damage to existing ground surfaces and vegetation.

What You Can Expect

Works will be managed through a secure, fenced work area accessed via the Luck Crescent car park. Temporary access controls and exclusion zones will help maintain public safety while deconstruction is underway. Ground protection will be installed along designated access routes, and environmental controls will remain in place throughout the project. Following completion, the site will be cleared, remaining piles removed and affected grassed areas reinstated as practicable to match the surrounding park. Updates will be provided through this Project Updates Hub as the project progresses.